Traction Motor Failures - PART 1
Large scale
Traction Motor failures in recent months reflect major short comings in
existing maintenance practices followed by sheds. 39 TM line failure cases have
been reported so far.
|
Item
|
Apr/09 to Dec/09
|
|||
|
Total
|
M
|
N
|
S
|
|
|
TM air duct
|
1
|
|
1
|
|
|
TM arc ring, cable terminal ,Teflon band
|
6
|
|
3
|
3
|
|
TM armature
|
5
|
3
|
2
|
|
|
TM bar cut
|
1
|
|
|
1
|
|
TM Bearing
|
7
|
2
|
1
|
4
|
|
TM carbon brush, holder spring
|
9
|
2
|
7
|
|
|
TM interpole, insulation
|
6
|
3
|
3
|
|
|
TM pinion
|
1
|
|
1
|
|
|
TM speed sensor
|
3
|
|
|
3
|
Sheds must implement following maintenance practices
in addition to existing practices followed.
· OVH and
testing of TM should be done as per format enclosed. Additional practices to be included by sheds
should be suggested so that uniform maintenance pattern can be followed in NF
railways.
· All TMs
requiring rewinding, IR attention, and magnet frame attention should be sent to
DMW.
· Sheds
should chalk out action plan in order to give focussed need based attention.
· Daily
one hour training for maintenance staff so that every sectional staff is well
conversant with overhauling and additional maintenance procedure.
· Exception
statement should be made for TMs running with low IR and high MV drop.
Action to be taken during trip maintenance:
Thoroughly clean TM with dry air and wipe with
slightly moist cloth dipped in Orion 77.
1.
Measure manomatric pressure during every trip. It should not be less than 90cm in WDM2
and 100 CM in WDG3 / WDM3.
2.
Measure TM temperature during incoming stage. TM
temperature variation beyond 60C in loco to be investigated.
3.
Check sign for flashover, sparking, high carbon
deposit etc. on armature.
Measure IR during every quarterly schedule. No fall in value from previous reading should be permitted.
4.
Check condition of end fittings, loose bolt, burnt
grease during every trip.
5.
check arc ring condition for sign of flashover,
missing bolts, loose bolts etc
6.
Premature wear of carbon brush or repeated breakage of
carbon brush is sign of major
7.
During M4 and above Sch. loosening of Insulator
Stud to be checked. Holder with
loose stud to be changed in-situ.
8.
TM should be taken out and examined in case of any
logging of fault code for TM high Temperature.
TM Carbon brush pigtail breakage:
1.
Check pigtail pull out pressure by spring balance.
2.
Apply adhesive over pigtail root.
3.
Use nylon tag to secure pigtail. This will eliminate
failure even if pigtails accidentally
come
out.
4.
Carbon brush to be changed in set only.
5.
If only one carbon brush is showing sign of wear /
damage, then thoroughly investigate the cause of wear of the carbon brush &
only after rectification of actual cause carbon brush should be changed.
Action to be taken during overhauling of TM :
Shed should add these maintenances instructions in
their overhauling practices.
|
S
N
|
Assy/
Sub assly
|
Cause of failure
|
Suggested Action plan
|
|
1.
|
TM Magnet frame
|
FIELD IR ZERO
|
1.
Field IR to be checked after baking in oven for 08
hrs.
2.
Final IR to be checked after watching it 03
days. It should remain at 500MΩ or above.
3.
Training to be given to staff to check IR after 3
days watching.
|
|
IP IR = 0
|
1.
0.38 MM Nomex paper packing should be provided
around all four-pole shoes.
2.
Back side of all pole shoes are to be insulated with
0.76m.m. Nomex paper.
3.
Pole shoe having sharp edge to be removed.
4.
Training to be given to staff to replace old mica
insulation and to fit standard size Nomex paper.
5. IR
value to be checked correctly by Million Mega Ohm eter, which would clearly shown the correct
IR value of IP with higher accuracy, by which
IR to be monitored Easily.
|
||
|
2.
|
TM ARM
|
ARMATURE IR
ZERO
|
1.
Armature IR should be checked after air blowing and
2 hrs. Oven heating. It should be 500
MΩ or above.
After cleaning vertically by Orion 77 it being baked in oven for 8
hrs. Final IR to be checked after
watching it 3 days. It should remain
at 500 MΩ or
above.
2.
Armature cooling hole to be blown by air through a
long perforated copper pipe, to ensure proper cleaning inside the armature..
3.
Training to be given to staff to check IR after
watching.3 days
4.
IR value
to be checked correctly by Million Mega Ohm Meter, which would clearly show
the correct IR value of Armature with
higher accuracy.
5.
Brazing to be done by Brazing Transformer only,
uniform heating of Brazing surface can be achieved by Brazing Transformer
only, Brazing by oxy-acetylene gas is to be avoided to prevent failure.
6.
A Surge comparison Tester is to be procured, on
available of this m/c inter turn short cut test is to be done extensively.
7.
MV drop is to be checked cautiously during sch
examination.
8.
During OVH of TM Armature, UST of Arm Shaft must
be done.
9.
Armature Shaft In-Situ UST of TM Armature to be
done during yearly sch. at the time of
Truck OVH.
10. Under cut the commutator
segments. It should be 0.030’ to 0.049’ (1.25 mm). Mica thickness shall
be1.5mm.Chamfer the commutator segment with tools having the angle of 60
degree. Polish the commutator surface with silicon paper.
|
|
3.
|
TM
BRG.
|
P/E BRG. SEIZED
|
1.
Radial clearance of bearing to be checked before
fitment and after fitment.
2.
During no load test temp rise of both side bearing
to be kept below P/E-9 degree & C/E-16’C strictly.
3.
Dominant frequency to be measured on vibration test bed
4.
Use SPM and engineer’s stethoscope.
5.
Do not refit old inner race.
6.
No Load Test should be done on a Test Stand
isolated from Earth Crust Vibration.
7.
Vibration velocity, acceleration and displacement
to be measured in 03 axes e.g. vertical. Horizontal and axial direction.
8.
Shock Pulses to be measured in terms of L.R. (Low
rate of occurrence of high shock value) and H.R. (High rate of occurrence of
low shock value) representing Bearing condition and Lube condition
respectively.
9.
RC & OBC measurement is to be done .i)R. C.
Bore Dia, ii) maximum and minimum value of Front and Rear Radial and
Diametric to be done. iii) O.B.C and R.C. slot width to be checked. iv)
O.B.C. inside Bore dia is to be measured.
|
|
C/E BRG. SEIZED
|
|||
|
4.
|
TM
Pinion
|
PINION TEETH
Broken
|
1.
Pinion having
life more than 15 yrs to be weeded out from service.
2.
Pinion having profile deviation more than 15 thou to
be rejected .
3.
100% Zyglow test to be done before fitment.
4.
D.P. test of Pinion during yearly sch. To be done.
5.
Pinion advance to be ensured.
|
|
5.
|
TM
Arc.
Ring
Loose
|
ARC RING
Mounting Bolt Loose
|
1.
100% arcing mounting bolts are to be replaced by M12
x 40mm long bolt. And both side of Arc ring to be welded properly in End
shield.
2.
Defective Arc Ring having damaged thread and heavy
flash mark are to be changed by new one.
|
|
6.
|
TM
Brush
Holder
|
INSULATOR
STUD,spring
Broken
|
1.
Single Unit Epoxy type Brush Holder to be procured
from reliable source and ARCO make brush holder to be replaced.
2.
During M4 and above Sch. loosening of Insulator
Stud to be checked. Holder with loose stud to be changed in-situ.
3.
All DMW/Motor holder connections to be checked
and half thread length bolts are to be replaced.
4.
DMW/PTA to
be informed, not to use half thread.
5.
Holder Lead connection to be checked properly for
any crack before fitment.
6.
Socket connection hole is to be checked for
oversize.
7.
Spring Tension of all holder pocket must be
checked and to be maintained at the value of 4.5 kg to 5.5 kg.
8.
During OVH of Holder Pocket must be checked for
any crack or defects.
|
|
|
|
Cables and terminals
|
1.
Visually examine cables and cables to replaced in
case of defective ,perished insulation
2.
Provide sleeve over cables for protection against
damage.
3.
Check condition of cables under cleat joint and
provide rubber cushioning.
4.
Securing of cables to prevent damage on run by
rubbing.
5.
Measure MV drop of terminal, replace terminals in
case of high MV drop.
|
|
7.
|
TM Carbon Brush
|
|
New carbon brushes received from store to be
modified by using araldite on pigtail groove and pigtail strings to be tied
up together by plastic make Cable Tie.
|
No comments:
Post a Comment