Power ground cases.
There have been a few line failure cases due to
power ground.
Details of Power
ground cases are given below:
|
Year
|
L
|
N
|
M
|
S
|
|
2009-2010
|
10
|
8
|
5
|
6
|
|
2010-2011
|
8
|
7
|
3
|
7
|
Sheds are requested to take following steps to control power ground
cases en route.
ROTATING MACHINES:-
Ø Check the IR Value; it
should not be less than 1 mega ohm for individual circuits separately.
Ø Generator components
should be free from dust and oil.
Ø Check the commutator
surface condition & condition of mica depth.
Ø Check chamfering of
commutator segment and sign of copper spreading.
Ø If attention is required due to poor TG
condition on above accounts then,
Ø Initially cut mica up
to 2.5 mm depth.
Ø Then chamfering of the commutator segment
should be done.
Ø After chamfering rub hacksaw blade inside mica
depth one round for clearing the copper dust trapped between the segments.
Ø Check the IR value of
armature it should be more than 1
mega ohm.
Ø Check the IR Value of
the inter pole as well as excitation field. Check the IR value of starting
field and excitation field.
Ø Check the carbon brush
holder saddle for ease of movement. If saddle is hard then explosive power
ground will be experienced.
Ø Mixed grade carbon
should not be used in traction machines. Carbon brush grade should be
identical.
Ø Holder insulator IR
should not be less than 50 mega ohms.
Ø All TG holder clearance
should be 0.090”.
Ø The alignment of carbon
brush pocket should be parallel with the commutator segment.
Ø The fitment of holder
should match with rocker arm marking.
Ø
Possibility of
shifting of rocker arm neutral axis should be checked. Though rarely observed.
Ø
Check VDP, WSR.RP
& EXCP for low IR.
Ø
All power switches
I.R should not be less than 100 mega ohms.
Ø
The Ground Relay
mechanical latch and resetting lever should lock properly failing which latch
will disengage at higher speed due to vibration without actually energizing the
relay coil.
Ø
Check TM arc ring
condition. Arc ring holding bolts should be of suitable size and from approved
source. DPT of bolts should be carried out during OVH. Thread locking compound
should be used.
Power Cables,
Power Control Cables &Power Panels:-
Ø Check the cable cleat for sign of cable damage.
Ø Check the cable hoses. The hoses should be
replaced in M24 and above schedule.
Ø Check the cable condition for rubbing, damage and
tear.
Ø Ensure that cables are not rubbing with loco body
or the traction motors.
Ø Check the IR Value of the backing piece of the
power contactors. The backing piece should be replaced in M48 schedule. Provide
additional nomex sheet in every major schedule.
Ø Dynamic braking grid should be checked for
insulation condition and additional P.U. sleeve should be put over insulator.